|
Contractor's
Duty to Discover Errors Under AIA A201 General Conditions: How Much Risk
Are You Really Taking?
Michael
J. Holden
Originally published June 2002
What
obligations does a contractor have to discover errors or inconsistencies
in the plans and specifications? Upon discovery of an error, what should
a contractor do?
Paragraph
3.2 of the AIA A201-1997 General Conditions, entitled "Review of
Contract Documents and Field Conditions by Contractor," attempts to
answer these questions. Specifically, subparagraph 3.2.1 sets forth the
following steps a Contractor shall take "before starting each
portion of the Work":
-
"carefully
study and compare" the drawings, other contract documents and
any owner-furnished surveys;
-
"take
field measurements of any existing conditions"; and
-
"observe
any conditions at the site" affecting the Work.
The
purpose of this review, according to the AIA general conditions, is to
facilitate construction rather than to discover errors, omissions or
inconsistencies in the Contract Documents. But if any errors,
inconsistencies or omissions are discovered during this three-step
process, the contractor must report them "promptly" to the
Architect.
A
Safe Harbor. What this paragraph seeks to accomplish is to provide a
"safe harbor" for contractors. If a contractor follows the
guidelines in subparagraph 3.2.1 for each portion of the work and
reports any discovered errors, then the contractor is free to construct
the project in accordance with the contract documents. In other words,
the owner retains the primary responsibility for design and the
contractor's only obligation is to report problems the contractor
actually recognized.
But
what happens if a contractor fails to complete each of these steps
before starting a portion of the work? For example, what if a contractor
does not take field measurements of existing conditions and such
measurements would have disclosed an error? Subparagraph 3.2.3 answers
this question-if a contractor fails to perform its obligations under
subparagraph 3.2.1, the contractor is liable for "such costs and
damages to the Owner as would have been avoided if the Contractor had
performed such obligations."
This
is the easy case. If the owner shows the contractor did not follow the
steps, then the contractor bears the loss.
Potential
Disputes Still Lurking. Even if a contractor can prove it performed
the three steps, however, an owner will still be able to challenge
whether the contractor's study and comparison was "carefully
performed;" whether the contractor took the proper field
measurements under the circumstances; and whether the contractor's site
observation was thoroughly conducted. Thus, while the provision seeks to
establish a bright line test-whether the contractor had actual knowledge
of the error-the door is still open for parties to dispute the
thoroughness of the contractor's investigation.
On a
related issue, there also may be disputes over what the contractor
actually knew; when the contractor actually made its discovery; and
whether the contractor provided "prompt" notice.
To
address these issues, one commentator has suggested that
"contractors may find it expedient to affirmatively report to the
Owner that it has completed its review [under subparagraph 3.2.1] and
has only a specific list of field conditions, code violations, or the
like to mention." (Sink and Petersen, The A201 Deskbook
[1998]). By following this advice, the contractor may thwart later owner
challenges.
Owners
Often Seek to Expand Contractor's Obligations. Many owners tinker
with the language in paragraph 3.1 to expand the contractor's
responsibilities for discovering errors and omissions. The most common
owner-requested change is to insert words such as "or that should
have been discovered" in the last sentence of both paragraphs 3.2.1
and 3.2.3.
This
minor insertion drastically alters the contractor's obligations. With
this language, the standard to evaluate the contractor's duty to
discover errors changes from a subjective one (what did the contractor
actually know) to an objective one (would an experienced, reasonably
prudent contractor have discovered the mistake). Since contractors
obviously do not want to assume this added burden, attempts to expand
the language should be vigorously resisted.
The
Bottom Line. Despite the open issues, paragraph 3.1 is generally a
good provision for both contractors and owners. It is clear that a
contractor must report errors it finds. But if a contractor follows the
steps in paragraph 3.2.1 and promptly reports any problems, then later
disputes over what a contractor knew or should have known may be
avoided. — Michael J. Holden
Relevant
Provisions in AIA A201-1997
3.2
REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
3.2.1
Since the Contract Documents are complementary, before starting each
portion of the Work, the Contractor shall carefully study and compare
the various Drawings and other Contract Documents relative to that
portion of the Work, as well as to the information furnished by the
Owner pursuant to Subparagraph 2.2.3, shall take field measurements of
any existing conditions related to that portion of the Work and shall
observe any conditions at the site affecting it. These obligations are
for the purpose of facilitating construction by the Contractor and are
not for the purpose of discovering errors, omissions, or inconsistencies
in the Contract Documents; however, any errors, inconsistencies or
omissions discovered by the Contractor shall be reported promptly to the
Architect as a request for information in such form as the Architect may
require.
3.2.2
Any design errors or omissions by the Contractor during this review
shall be reported promptly to the Architect but it is recognized that
the Contractor's review is made in the Contractor's capacity as a
Contractor and not as a licensed design professional unless otherwise
specifically provided in the Contract Documents. The Contractor is not
required to ascertain that the Contract Documents are in accordance with
applicable laws, statutes, ordinances, building codes, and rules and
regulations, but any nonconformity discovered by or made known to the
Contractor shall be reported promptly to the Architect.
3.2.3
If the Contractor believes that additional cost or time is involved
because of clarifications or instructions issued by the Architect in
response to the Contractor's notices or requests for information
pursuant to Subparagraphs 3.2.1 and 3.2.2, the Contractor shall make
Claims . . . If the Contractor fails to perform the obligations of
Subparagraphs 3.2.1 and 3.2.2, the Contractor shall pay such costs and
damages to the Owner as would have been avoided if the Contractor had
performed such obligations. The Contractor shall not be liable to the
Owner or Architect for damages resulting from errors, inconsistencies or
omissions in the Contract Documents or for differences between field
measurements or conditions and the Contract Documents unless the
Contractor recognized such error, inconsistency, omission or difference
and knowingly failed to report it to the Architect.
|