|
Possible
Basis for Claim: Breach of Implied Duty
Not to Hinder or Delay
Michael
J. Holden
Originally published June 2002
Owners
and contractors realize that they must read the construction contract to
determine their respective rights and obligations. But the express terms
of the contract do not necessarily set forth the entire agreement.
Courts have recognized that there are many implied obligations between
contracting parties that are not included in the written words of the
contract.
One
obligation that exists in every contract is the implied duty to
cooperate and not hinder performance. It is widely recognized that every
contract includes an implied condition of cooperation; parties to a
contract impliedly warrant not to hinder the other party's performance.
This
duty is rooted in the well settled principle that every contract imposes
upon each party a duty of good faith and fair dealing in its performance
and enforcement. For example, Restatement (Second) of Contracts § 205
states: "Every contract imposes upon each party a duty of good
faith and fair dealing in its performance and its enforcement."
In
order to recover for breach of this implied duty, the contractor must
prove that the owner's conduct during construction was unreasonable and
the conduct caused actual delay. Whether an owner has breached its
implied duty is determined by the reasonableness of the conduct under
the circumstances. A contractor cannot recover if the owner's conduct is
determined to be reasonable or justified.
Active
Owner Interference. The duty can be breached by active owner
interference. Courts have held owners liable for hindering or
interfering with performance under many different factual scenarios.
Examples include restricting the manner of performance; directing the
contractor to perform in a specific way; taking action that damages the
work site; removing the contractor's project manager; unjustifiably
rejecting work; or overzealous inspection.
In Lester
N. Johnson v. City of Spokane, 22 Wash. App. 265, 588 P.2d 1214
(1970), for example, the owner admitted pumping raw sewage into the
project site of a contractor hired to perform work on the owner's sewage
system. The owner attempted to avoid liability by arguing that a
contract provision allowed the owner to perform work at or near the
project site. The court rejected the owner's defense and ruled that the
action of spewing raw sewage over the project site was not contemplated
or provided for in the parties' agreement and therefore represented a
breach of the warranty of cooperation.
Owner's
Lack of Cooperation. The duty can also be breached by the owner's
lack of cooperation. Examples include the owner failing to provide
access to the project site; failing to respond to a contractor's request
for information; delays in inspection; failing to timely review
submittals; failing to process change orders in a timely manner; failing
to help in formulating a solution to a construction problem; site
availability; and failing to coordinate among other contractors on site.
Implied
Duty Also Exists Between Generals and Subs. The implied duty to
cooperate also exists between general contractors and subcontractors. In
other words, in every contract between a contractor and subcontractor,
the contractor impliedly promises not to do anything to prevent, hinder
or interfere with the subcontractor in its performance.
In
United States ex rel. E & R Construction v. Guy H. James
Construction Co., 390 F.Supp. 1193 (D.C. Tenn. 1972), for example,
the court held that a subcontractor was entitled to damages as a result
of a general contractor interfering with or hindering the
subcontractor's performance. There, the subcontractor was required to
stockpile impervious fill on the project at a designated location. After
the subcontractor created two stockpiles but before the material was
accepted or used, contractor contaminated the stockpiles by constructing
a shot rock road across the entire length of the first stockpile and
dumping waste rock on the second stockpile.
The Guy
H. James court held that a general contractor had a duty to exercise
care in its work as to not materially interfere with the work of the
subcontractor. The measure of damages was the added cost involved in the
unanticipated handling and hauling of material necessitated by the
general contractor's conduct. — Michael
J. Holden
|